Slack and critical tasks

About Slack or „float”
Slack or „float” is the amount of time that a task can slip before it affects another task or the project's finish date. Use the „Early Start”, „Early Finish”, „Late Start”, „Late Finish”, „Start Slack”, and „Finish Slack” fields to analyze project schedule delays and find available slack in your schedule.

  1. Choose „Task Sheet” (or any other task view with a table portion) > „Schedule Table” in the „Views” toolbar icon.
  2. Review the values in the „Free Slack” and „Total Slack” column.

Note
Slack values may also indicate a schedule inconsistency. For example, a negative slack value occurs when one task has a „Finish-to-Start” dependency with a successor task, but the successor task has a „Must Start On” constraint that is earlier than the end of the first task.

About critical tasks
By default, iTaskX defines a task as critical if it has zero days of slack. However, you can change this definition and make a task critical if it has, for example, one or two days of slack. Making a task with slack critical can be helpful if you want to be alerted to tasks that are becoming critical when you still have some buffer.
Slack is determined by the early finish and late finish dates of the tasks in your schedule. An early finish date is the earliest date that the task could finish, based on its start date and scheduled duration. A late finish date is the latest date that the task can finish without delaying the project finish. The difference between early finish and late finish dates determines the amount of slack.
For critical path tasks (tasks that have no slack), the early finish and late finish dates are identical.

  1. Choose „Edit” > „Project Options…” or use the Project Options toolbar icon.
  2. Click on the „Calculation” tab and enter the new slack value.
  3. Press „OK” to leave the „Project Options” sheet.
  1. In the „View Options and Styles” window Format Window activate the „Indicate Critical Tasks” check box.

Note
By default, critical tasks are marked red. To use a differnt color change the „Attention” color in the „View Options and Styles” window Format Window.

Shorten the critical path
If you want to bring in the project finish date, you need to bring in the dates of your critical path tasks. This is also known as crashing a project.
To do this:

  • Shorten the duration or work on a task on the critical path.
  • Change a task constraint to allow for more scheduling flexibility.
  • Break a critical task into smaller tasks that can be worked on simultaneously by different resources.
  • Revise task dependencies to allow more scheduling flexibility.
  • Set lead time between dependent tasks where applicable.
  • Schedule overtime.
  • Assign additional resources to work on critical path tasks.

Note
If you bring in the dates of your critical path, a different series of tasks could become the new critical path.
There is always one overall critical path for any project schedule. The new critical path would then become the series of tasks you track more closely to ensure the finish date you want.

Cookie Usage

We use cookies (including third-party cookies), to provide you with the best possible online experience and to tailor content to your interests. By clicking on „Accept all” you agree to the saving and reading of information on your end device. You also agree to the further processing of the collected and read personal data in addition to the possible transfer to countries outside of the EU, for example the US.
For detailed information on the use of cookies, please click on „Learn more”. By clicking on „Reject”, you reject the use of cookies that require consent.

Learn more
Reject Accept all

Thank you!

We received your request.

Upgrade existing iTaskX lincense

Drop an iTaskX license-file (or click) to start the upgrade process.
(Max. 1 file - .itaskx3license, .itaskx4license or .itaskx6license)

This license could not be upgraded!

Error: This trial-license cannot be upgraded!
If you have any questions, please contact us at support@techno-grafik.com

License Upgraded Successfully!

Since you purchased your license after 04/30/2023, we could upgrade it to iTaskX 6 for free.
Click here to download your License

(This link is valid only for the next 5 minutes!)
Note, the new license was also mailed to „ ”.

License may be upgraded!

This is your upgrade coupon code: XXX-XXX-XXX-XXX
Click here to buy your License now

The coupon code was also sent per mail to „ ”.