Linking tasks

After tasks are created in a project, they should be linked to show relationships between them.

To model realistically projects iTaskX offers the following link types:

Finish-to-Start (FS)

Finish-to-start Link
The dependent task (B) can't begin until the task that it depends on (A) is complete.
For example, if you have two tasks, „Dig foundation” and „Pour concrete”, the „Pour concrete” task can't begin until the „Dig foundation” task is completed.

Start-to-Start (SS)

Start-to-start Link
The dependent task (B) can't begin until the task that it depends on (A) begins.
The dependent task can start at any time after the task that it depends on begins. The „Start-to-Start” link type does not require that both tasks begin at the same time.
For example, if you have two tasks, „Pour concrete” and „Level concrete”, the „Level concrete” task can't begin until the „Pour concrete” task begins.

Finish-to-Finish (FF)

Finish-to-finish Link
The dependent task (B) can't be completed until the task that it depends on (A) is completed.
The dependent task can be completed at any time after the task that it depends on is completed. The „Finish-to-Finish” link type does not require that both tasks be completed at the same time.
For example, if you have two tasks, „Add wiring” and „Inspect electrical”, the „Inspect electrical” task can't be completed until the „Add wiring” task is completed.

Start-to-Finish (SF)

Start-to-finish Link
The dependent task (B) can't be completed until the task that it depends on (A) begins.
The dependent task can be completed at any time after the task that it depends on begins. The „Start-to-Finish” link type does not require that the dependent task be completed concurrent with the beginning of the task on which it depends.
For example, the roof trusses for your construction project are built off-site. Two of the tasks in your project are „Truss delivery” and „Assemble roof”. The „Assemble roof” task can't be completed until the „Truss delivery” task begins.

Link tasks:

  1. Select two or more tasks you want to link.
    - To select non-adjacent tasks, hold down „COMMAND” ⌘ key, and then click the tasks you want to link.
    - To select adjacent tasks, hold down „SHIFT” ⇧ key, and then click the first and last tasks you want to link.
  2. Click on the „Link” Link Tasks mini toolbar icon and choose the link type you want.

Lead and lag time:

Lead time is overlap between tasks that have a dependency. For example, if a task can start two days before its predecessor is finished, you can specify a „Finish-to-Start” dependency with a lead time of 2 days for the successor task. You enter lead time as a negative value „-2d”.
Lag time is a delay between tasks that have a dependency. For example, if you need a two-day delay between the finish of one task and the start of another, you can establish a „Finish-to-Start” dependency and specify two days of lag time. You enter lag time as a positive value „2d”.

Notes

  • It's also possible to create „Finish-to-Start”, „Start-to-Start”, „Finish-to-Finish”, or „Start-to-Finish” links with the mouse in the Gantt Chart. To create a link between two tasks with the mouse in the „Gantt Chart”, click on the desired task bar and drag the mouse up or down until the cursor change into a chain, then release the mouse over the target task bar.
  • You can also create links by entering values in the „Predecessor” or „Successor” field. Each task link is represented by its task ID number, which may be followed by a dependency type and the lead or lag time.
    For example, 7FS+3d in the „Predecessor” field means that task 7 is a predecessor of this task, with a „Finish-to-Start” dependency and a 3 day lag time.
  • To change link values, you can simply enter the new values in the „Predecessor” or „Successor” field or do this in the „Info” inspector in the „Predecessor” or „Successor” pane.

Remove a task link:

  1. Select the task(s) you want to unlink.
    - To select non-adjacent tasks, hold down „COMMAND” ⌘ key, and then click the tasks you want to unlink.
    - To select adjacent tasks, hold down „SHIFT” ⇧ key, and then click the first and last tasks you want to unlink.
  2. Click on the „Unlink” Unink Tasks mini toolbar icon or use the „-” button from the „Info” inspector „Predecessor” / „Successor” pane.
Cookie Usage

We use cookies (including third-party cookies), to provide you with the best possible online experience and to tailor content to your interests. By clicking on „Accept all” you agree to the saving and reading of information on your end device. You also agree to the further processing of the collected and read personal data in addition to the possible transfer to countries outside of the EU, for example the US.
For detailed information on the use of cookies, please click on „Learn more”. By clicking on „Reject”, you reject the use of cookies that require consent.

Learn more
Reject Accept all

Thank you!

We received your request.

Upgrade existing iTaskX lincense

Drop an iTaskX license-file (or click) to start the upgrade process.
(Max. 1 file - .itaskx3license, .itaskx4license or .itaskx6license)

This license could not be upgraded!

Error: This trial-license cannot be upgraded!
If you have any questions, please contact us at support@techno-grafik.com

License Upgraded Successfully!

Since you purchased your license after 04/30/2023, we could upgrade it to iTaskX 6 for free.
Click here to download your License

(This link is valid only for the next 5 minutes!)
Note, the new license was also mailed to „ ”.

License may be upgraded!

This is your upgrade coupon code: XXX-XXX-XXX-XXX
Click here to buy your License now

The coupon code was also sent per mail to „ ”.