Resolving resource over allocation

A resource is over allocated when it is assigned too much work to complete within the resource available time. You can resolve resource over allocations by adjusting either tasks or resources in your project.

Under „Messages” Massages in the „Navigation” area Show or hide the navigation area you get a warning for every over allocated resource. Over allocated resources are also marked red by default in the „Resource Sheet” view.

A resource overallocation can be caused by:

  • A resource assigned to work full-time on more than one task at the same time.
    For example, if you assign a full-time resource to two tasks of eight hours each on the same day, then the resource is over allocated because only one eight-hour task can be accomplished on that day.
    To view a resource workload in iTaskX Pro, choose „Resource Usage” > „Work Table” in the „Views” toolbar icon. Look at the number of tasks assigned during times of over allocation.
  • Increased duration of tasks.
    If you increase a tasks duration, then the amount of work assigned to the resource also increases and may cause the resource to have too much work at one time. To view a resource workload in iTaskX Pro, choose „Resource Usage” > „Work Table” in the „Views” toolbar icon. Look at the number of hours of work assigned.
  • Decreased unit availability for resources.
    For example, a resource availability is reduced from 100% units to 50% units because it is working part-time. Or, more specific non-working time is entered on the resource calendar.
    To see if non-working time is entered on the resource calendar, select „Working Times...” from the „Edit” menu at the top of your screen or use the Working Times toolbar icon and choose the calendar which is used for the resource.
Cookie Usage

We use cookies (including third-party cookies), to provide you with the best possible online experience and to tailor content to your interests. By clicking on „Accept all” you agree to the saving and reading of information on your end device. You also agree to the further processing of the collected and read personal data in addition to the possible transfer to countries outside of the EU, for example the US.
For detailed information on the use of cookies, please click on „Learn more”. By clicking on „Reject”, you reject the use of cookies that require consent.

Learn more
Reject Accept all

Thank you!

We received your request.

Upgrade existing iTaskX lincense

Drop an iTaskX license-file (or click) to start the upgrade process.
(Max. 1 file - .itaskx3license, .itaskx4license or .itaskx6license)

This license could not be upgraded!

Error: This trial-license cannot be upgraded!
If you have any questions, please contact us at support@techno-grafik.com

License Upgraded Successfully!

Since you purchased your license after 04/30/2023, we could upgrade it to iTaskX 6 for free.
Click here to download your License

(This link is valid only for the next 5 minutes!)
Note, the new license was also mailed to „ ”.

License may be upgraded!

This is your upgrade coupon code: XXX-XXX-XXX-XXX
Click here to buy your License now

The coupon code was also sent per mail to „ ”.